Project Coordination and Monitoring Unit (PCMU)

Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) & Urban Resilience Project (URP)

Programming Division, Planning Commission, Ministry of Planning

DLS Part

Department of Livestock Services (DLS) Part

 

01. Project Title : Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP): Support for Agriculture (Sub-Com: A2) DLS Part (2nd Revised)
02. a) Sponsoring Ministry/Division : Ministry of Fisheries & Livestock (MOFL)
b) Executing Agency : Department of Livestock Services (DLS) &Food and Agriculture Organization of the UN
03. Objective of the Project: 

Rapidly rebuild the livelihoods, dignity and food security of worst affected landless and resourceless poor people through Livestock activities of 13 Upazilas of 6 severely affected districts in Barisal and Khulna areas by cyclone SIDR 2007.

 

04. Location of the Project
  Division District Upazila
a) Khulna Bagerhat Sarankhola, Morrelganj
b) Barisal Pirojpur Mathbaria, Bhandaria
Barguna Patharghata, Sadar Barguna, Amtali, Bamna
Patuakhali Mirjagonj, Galachipa, Kalapara
Jhalokathi Kathalia
Barisal Barisal Sadar
05. Project Implementation Period : a) Original 01 July, 2008 to 30 June, 2013
b) 1st Revised 01 July, 2008 to 30 June, 2014
c) 2nd Revised 01 July, 2008 to 30 June, 2014

 

06. Revised Cost of the Project
Source Original 1st Revised 2nd  Revised
a) GoB
b) DPA 3,447.50 6,026.23 6,740.28
c) RPA
d) Total 3,447.50 6,026.23 6,740.28
Disclaimer: Official use only.