DLS Part
Department of Livestock Services (DLS) Part
01. | Project Title | : | Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP): Support for Agriculture (Sub-Com: A2) DLS Part (2nd Revised) | |
02. | a) | Sponsoring Ministry/Division | : | Ministry of Fisheries & Livestock (MOFL) |
b) | Executing Agency | : | Department of Livestock Services (DLS) &Food and Agriculture Organization of the UN | |
03. | Objective of the Project:
Rapidly rebuild the livelihoods, dignity and food security of worst affected landless and resourceless poor people through Livestock activities of 13 Upazilas of 6 severely affected districts in Barisal and Khulna areas by cyclone SIDR 2007. |
04. | Location of the Project | ||||||||
Division | District | Upazila | |||||||
a) | Khulna | Bagerhat | Sarankhola, Morrelganj | ||||||
b) | Barisal | Pirojpur | Mathbaria, Bhandaria | ||||||
Barguna | Patharghata, Sadar Barguna, Amtali, Bamna | ||||||||
Patuakhali | Mirjagonj, Galachipa, Kalapara | ||||||||
Jhalokathi | Kathalia | ||||||||
Barisal | Barisal Sadar | ||||||||
05. | Project Implementation Period | : | a) | Original | 01 July, 2008 to 30 June, 2013 | ||||
b) | 1st Revised | 01 July, 2008 to 30 June, 2014 | |||||||
c) | 2nd Revised | 01 July, 2008 to 30 June, 2014 | |||||||
06. | Revised Cost of the Project | ||||
Source | Original | 1st Revised | 2nd Revised | ||
a) | GoB | – | – | – | |
b) | DPA | 3,447.50 | 6,026.23 | 6,740.28 | |
c) | RPA | – | – | – | |
d) | Total | 3,447.50 | 6,026.23 | 6,740.28 |