Project Coordination and Monitoring Unit (PCMU)

Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) & Urban Resilience Project (URP)

Programming Division, Planning Commission, Ministry of Planning

DOF Part

Department of Fisheries (DOF) Part

 

01. Project Title : Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP): DOF Part (2nd Revised)
02. a) Sponsoring Ministry/Division : Ministry of Fisheries & Livestock (MOFL)
b) Executing Agency : Department of Fisheries (DOF)
03. Objectives of the Project:
i) To restore the aquaculture production chain in the cyclone affected coastal areas providing aquaculture inputs to the coastal fish farmers.
ii) To restore the livelihood of cyclone affected coastal fishers providing fishing nets and repair their boats.
iii) To aware coastal fishers/farmers about cyclone enabling them to save their lives and properties.
iv) To ensure the steady economic growth in the fisheries sector of the coastal region.
v) Improve knowledge base on existing status of coastal fishers and small-scale fisheries.
04. Location of the Project

 

  Division District Upazila
a) Khulna Bagerhat Sarankhola, Morrelganj
b) Barisal Pirojpur Mathbaria, Bhandaria
Barguna Patharghata, Sadar Barguna, Amtali, Bamna
Patuakhali Mirjagonj, Galachipa, Kalapara
Jhalokathi Kathalia
Barisal Barisal Sadar

 

05. Project Implementation Period : a) Original July, 2008 to June, 2013
b) 1st Revised July, 2008 to June, 2014
c) 2nd Revised July, 2008 to June, 2014
06. Revised Cost of the Project
Source Original 1st Revised 2nd  Revised
a) GoB
b) DPA 3,447.50 6,026.23 6,138.75
c) RPA
d) Total 3,447.50 6,026.23 6,138.75

 