Project Coordination and Monitoring Unit (PCMU)

Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) & Urban Resilience Project (URP)

Programming Division, Planning Commission, Ministry of Planning

LGED Part

Local Government Engineering Department (LGED) Part

 

01. Project Title : Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP): Local Government Engineering Department (LGED) Part (2nd Revised)
02. a) Sponsoring Ministry/Division : Ministry of Local Government, Rural Development & Co-operatives/Local Government Division (LGD)
b) Executing Agency : Local Government Engineering Department (LGED)
03. Objectives of the Project:
i) Provide safe shelter to human being and their resources including domestic animals during natural calamities like Super Cyclone (Sidr) and tidal surge.
ii) Create facilities for primary education and thereby facilitate education for all.
iii) Create direct short-term employment opportunities through project construction works and a few regular employment through other use of the shelters.
iv) Create facilities to community purpose such as various social and Govt. Program like EPI, NGO training etc.
04. Location of the Project

 

  Division District Upazila
  Barisal Barguna, Barisal, Bhola, Jhalokathi, Patuakhali and  Pirojpur. 65 Upazilas of 9 Districts.
Khulna Bagerhat, Khulna and Satkhira,

 

05. Project Implementation Period : a) Original August, 2008 to June, 2013
b) 1st Revised August, 2008 to June, 2014
c) 2nd Revised August, 2008 to December, 2017
06. Revised Cost of the Project
Source GoB RPA DPA Total
Through GoB Special Account
a) Original 133.25 27,838.12 992.88 28,959.25
b) 1st Revised 372.22 89,157.60 89,529.82
c) 2nd Revised 795.00 194,375.00 195,170.00
Disclaimer: Official use only.