Project Coordination and Monitoring Unit (PCMU)

Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) & Urban Resilience Project (URP)

Programming Division, Planning Commission, Ministry of Planning

PCMU Part

Project Coordination and Monitoring Unit (PCMU) Part

 

01. Project Title : Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP): Project Coordination and Monitoring Unit (PCMU) (2nd Revised)
 
02. a) Sponsoring Ministry/Division : Ministry of Planning (MOP)/Planning Division
b) Executing Agency : Programming Division, Planning Commission.

 

03. Objectives of the Project:
i) Coordination, Monitoring and Evaluation of the Emergency Cyclone Recovery and Restoration Project (ECRRP) as a whole;
ii) Management of need based strategic studies and other studies/pilot projects that may emerge during the Project Implementation;
iii) Management of Local and Foreign Training on Disaster Management & Preparedness, Contract Management, Financial Management, Environmental & Social Assessment; and
iv) Support to emergency recovery from the future disaster, if any, occurs during the Project Implementation period.

 

04. Location of the Project
  Division District Upazila
a) Dhaka Dhaka N/A

 

05. Project Implementation Period : a) Original August, 2008 to June, 2013
b) 1st Revised August, 2008 to June, 2014
c) 2nd Revised August, 2008 to December, 2017

 

06. Cost of the Project
Source GoB

RPA

DPA Total
Through GoB Special Account
a) Original 226.15 11,514.50 11,740.65
b) 1st Revised 226.15 6,205.50 6,431.65
c) 2nd Revised 488.00 12,800.00 13,288.00